• RU
  • icon Waiting For Moderation: 30
Menu

Mall Fire Alert

  • Added: 28.07.2014
  • Size: 8 MB
  • Downloads: 1
Find out how to download this material

Description

In accordance with the requirements of the Code of Rules SP 3.13130.2009, a warning and evacuation management system of type 3 (SOME-3) was developed for the shopping and office center. The developed EPSS system is an integral part of the complex of engineering and technical systems for fire protection of the building and provides: - division of the building into warning zones; - transmission of voice messages and special pre-recorded texts both to a separately selected zone, a group of zones, and to all zones at the same time; - transmission of voice messages from remote microphone consoles, with the possibility of selection of translation zones; - provision of notification of evacuation of people with hearing impairment by means of light stroboscopic annunciators; - possibility of implementation of several options of evacuation plans from each zone; - coordinated control from one fire department of the building systems ensuring safety of people in case of fire; - round-the-clock operation of all equipment and prompt transmission of voice messages about the occurrence of a fire, about escape routes, as well as about any emergency situations throughout the building; - possibility of operation in the mode of voice messages translation via EMSS network (announcements, instructions), as well as disconnection of this mode at reception of "FIRE" signal with switching to fire warning mode according to the specified algorithm; - check of equipment serviceability and integrity of EPSS lines and circuits; - operation of warning system in case of loss of main power supply (220V 50Hz) required for complete evacuation of people;

Project's Content

icon
icon
icon 00_ТЛ.doc
icon 01.04_-01.06_ОД_Условные.bak
icon 01.04_-01.06_ОД_Условные.dwg
icon 01.1-01.3_ОД.doc
icon 02_ПОЯСНИТЕЛЬНАЯ.doc
icon 03_СХЕМЫ.bak
icon 03_СХЕМЫ.dwg
icon 12_ПОДКЛЮЧЕНИЕ.bak
icon translation
icon 13_СО.doc
icon Карусель гипермаркет с ТХ план ПС.bak
icon Карусель гипермаркет с ТХ план ПС.dwg
icon Карусель гипермаркет с ТХ план ПС.dwl
icon Карусель гипермаркет с ТХ план ПС.dwl2
icon
icon ТЗ на заземление_ПО.doc
icon ТЗ на электроснабжение_ПО.doc

Additional information

Purpose of the installation

In accordance with the requirements of the Set of Rules SP 3.13130.2009, a type 3 warning and evacuation control system (SOOE3) has been developed for the shopping center.

The developed EPSS system is an integral part of the complex of engineering systems for fire protection of the building and provides:

dividing the building into warning areas;

transmitting voice messages and special pre-recorded texts both to a separately selected zone, a group of zones, and to all zones simultaneously;

transmission of voice messages from remote microphone consoles, with the possibility of selecting translation zones;

provision of notification about evacuation of people with hearing impairment, by means of light stroboscopic annunciators;

the possibility of implementing several options for evacuation plans from each zone;

coordinated control from one fire department of the building systems ensuring safety of people in case of fire;

24-hour operation of all equipment and prompt transmission of voice messages about the occurrence of a fire, about escape routes, as well as about any emergency situations throughout the building;

possibility of operation in the mode of voice messages (announcements, instructions) broadcast via the EMSS network, as well as shutdown of this mode at reception of "FIRE" signal with switching to the fire warning mode according to the specified algorithm;

check of equipment serviceability and integrity of EPSS lines and circuits;

operation of the warning system in case of loss of main power supply (220V 50Hz) required for complete evacuation of people;

3. Technical solutions

The selection of equipment for the construction of the EMSS system was made on the basis of the requirements for the system. The fire warning and evacuation management system was designed using 600 series equipment from InterM (Korea).

Fire warning system includes:

Central equipment

- Alarm panel "EP616";

- Audio signal distributors "PE-606";

- Warning system controller "ECS616";

- Translation line control unit "SC624";

- Digital tape recorder "PV632A";

- 480W power amplifiers "PA648";

- 360Vt power amplifiers "PA636";

- Power amplifiers 240Vt "PA624";

Message Playback Equipment in Alert Areas

- Loudspeaker, 10 W, 90 dB, 15012000 Hz, "SWS10";

- Loudspeaker, 3 W, 89 dB, 18010000 Hz, "SWS03";

- Remote microphone console "RM616";

- Lightning annunciators "Light220";

Additional equipment

- Power supply units "PD659";

- Power expander "PD658";

- Charger "PB607";

- Batteries.

Central equipment is installed in 19 "equipment cabinets and is located in the security room on the 1st floor (pom. 112),. Power supply of the central equipment 220V 50Hz is provided according to the I category of power supply with redundancy. The use of redundant power supplies enables uninterrupted power supply of the central equipment when the main primary power supply of the sources (220 V 50Hz) disappears, due to the energy of the storage batteries.

In the security room on the 1st floor, install emergency lighting and provide artificial lighting of at least 150 lux for fluorescent lamps and at least 100 lux for incandescent lamps. Emergency lighting shall provide illumination on working surfaces of at least 10% of the corresponding standards. Provide measures excluding access of unauthorized persons to EMSS equipment.

Remote microphone consoles of the warning subsystem are installed in the administration room on the 1st floor.

Power supply of the peripheral equipment of the EPSS system is provided from the central equipment installed in the security room via communication lines.

Power supply of "EXIT" annunciator is performed from emergency lighting panel.

In the premises of the building, voice annunciators are installed, according to the drawings, and are connected to the power warning lines provided by the drawings. The alert lines are connected to the amplifiers at 100V terminals.

4. System operation

The warning subsystem is started automatically by the signal of the automatic fire alarm system, according to the algorithm programmed in it.

Signals of automatic warning start from the automatic control system are transmitted to ECS1 unit inputs. The system controller controls the activation of alert lines and the operation of translation amplifiers. The algorithm of automatic warning start is determined during programming of automatic fire alarm system operation.

In the case of manual notification, as well as voice messages, in the voice message transmission line (out of 11 possible), the operator selects by pressing the corresponding buttons on the microphone consoles RM1.

5. Electrical wiring.

Installation of EMSS warning lines is carried out by open laying method, with the condition of their integrity monitoring along the entire length. Connections and branches of wires and cables are made in junction or junction boxes by soldering or by means of screws.

The distribution network of the warning system is made by the VBGngFRLS cable in PVC pipes rigid along the walls and floors (as per drawings).

Switching between EMSS central equipment devices is performed by different types of cables, as per drawings, as well as cables included in the equipment supply package.

Vertical laying of cables and wires of the ECSS system, between floors, is provided in a low-current riser made of two PVC pipes with smooth rigid dy = 63 mm.

6. Power supply and grounding (connection)

According to the degree of reliability of the power supply, automatic fire protection units are consumers of reliability category I and must be provided with electricity from two independent mutually redundant power supplies, and their power supply interruption in case of power supply failure from one of the power supplies can be allowed only for the time of automatic power recovery.

If there is one power supply, it is allowed to use fire protection units, storage batteries or uninterruptible power supply units as a backup power supply source, which must provide power to the specified electric receivers in standby mode for 24 hours and in "Alarm" mode for at least 3 hours.

Power supply of light stroboscopic annunciators is provided with project 04511APM, with a constant voltage of 24B, with reservation.

Grounding (boring) of equipment shall be performed in accordance with "Electrical Installation Rules," seventh edition (PUE); SNiP 3.05.068 "Electrical Devices"; requirements of GOST 12.1.03087, and technical documentation of manufacturers of components. Protective grounding (ground) resistance must be not more than 4.0 Ohm.

All metal parts of electrical equipment that are not normally energized, but which may be energized due to insulation failure, shall be grounded (grounded).

Power supply of the central equipment of the EMSS system (devices located in the hardware cabinets 19 ") 220V 50Hz is performed by cables included in the equipment supply set, from plug sockets of the distribution and separation power system connected according to the I category of reliability of power supply.

The following devices of the EMSS system are subject to grounding (earthing):

- metal housings of the ESMS central equipment located in the hardware cabinets in the security room;

- 19 "metal equipment cabinets located in the security room;

Grounding of the hardware cabinets 19 "and the housings of the equipment installed in them should be performed by a separate cable from the grounding bus of the power panel (performed by the section of internal electrical networks). Connect the equipment rack and housings of ESDS equipment to the grounding bar by bolting.

7. Instructions for erection of ECSS

7.1 Locations of equipment and cable routes on the drawings are shown conditionally and specified during installation.

7.2 Installation shall be performed in a certain sequence:

- check of embedded pipes for wire pass-through;

- install wires;

- install the annunciators;

- install the instruments;

- connect alert lines in turn;

- perform commissioning of the system.

7.3 Perform wiring of the EMSS system and warning lines separately from wiring of other systems. Wiring of warning and control networks should be laid away from lines with high voltage or high currents. All connections and interunit connections shall be made in strict accordance with the requirements of the operating manuals and equipment.

7.4 Products and materials used in the performance of works shall comply with the project specifications and have appropriate certificates, technical passports and other documents certifying their quality.

When laying lines behind panels and suspended ceiling, lay pro-water in bundles.

Avoid parallel routing of wiring links.

7.5 Do not leave the ends of feed lines bare when attached under the clamp.

7.6 Power cables, grounding conductors shall be laid in accordance with the requirements of "Electrical Installations Design Rules" (PUE), "Installation Instructions for Communication, Broadcasting and Television Devices Structures" VSN 60081 of the Ministry of Communications of the Russian Federation.

8. Information on the organization of installation works

Start the work on erection of the EMSS system hardware within the terms stipulated by the contract. At the same time, the following preparatory work shall be carried out by the installation and installation organization:

- design documentation has been adopted and studied;

- studied the construction part of the SNiP 3.05.0685 facility;

- received from the Customer (Gene. Contractor) materials, equipment of the EPSS system to be installed, in quantity and nomenclature, provided by the project; the presence of electric lighting in the installation area was checked;

- design of works execution in accordance with RD 78.14592 or inspection acts has been developed and approved.

Equipment of the EMSS system, materials, technical documentation of manufacturers (passport, installation and operation instructions for technical equipment, certificates for materials) are transferred by the Customer (Gene. Contractor) of the installation and installation organization in order and within the terms established by the current "rules on relations between the organizations - General Contractors and Subcontractors" and the schedule for the supply of materials.

9. Maintenance and maintenance of EPSS system

The main purpose of maintenance is to carry out measures aimed at maintaining the EMSS system in a state of readiness for operation, preventing faults and premature failure of component devices and system elements.

The maintenance structure includes the following activities:

- maintenance;

- scheduled maintenance;

- planned overhaul;

- unscheduled repair.

Observation of planned work of a system, elimination of the found defects, adjustment, control, approbation and check belongs to maintenance.

The scope of maintenance includes partial disassembly, replacement or repair of wires and cable structures. Measurements and tests of equipment and elimination of detected defects are carried out.

The scope of overhaul, in addition to the work provided for by the current repair, includes the replacement of worn out system elements and improvement of equipment operational capabilities.

Unscheduled repairs are carried out in the scope of current or major repairs and are carried out after a fire, accident caused by unsatisfactory operation of the equipment or to prevent it.

During maintenance works, the requirements of "Instructions for organization and performance of works on regulated maintenance of fire extinguishing, fire and fire protection alarm units," RD 25.96490 "System for maintenance and repair of ACS, smoke removal, security, fire and fire protection alarm" should be followed.

Drawings content

icon 01.04_-01.06_ОД_Условные.dwg

icon 03_СХЕМЫ.dwg

03_СХЕМЫ.dwg

icon Карусель гипермаркет с ТХ план ПС.dwg

up Up