• RU
  • icon Waiting For Moderation: 30
Menu

Server Power and Microclimate Monitoring System

  • Added: 30.08.2014
  • Size: 2 MB
  • Downloads: 3
Find out how to download this material

Description

The system for monitoring the power supply parameters of the server equipment and the microclimate parameters in the server room with SMS - notification of deviation of monitored parameters from the norm, indication of monitored parameters on the front panel of the board, indication and sound warning on the remote panel is implemented, an animated GIF with the appearance of the assembled panel is attached. Drawings, Operating Manual

Project's Content

icon
icon инструкция по эксплуатации.doc
icon схемы.dwg
icon собранный щит (GIF-анимация).gif

Additional information

Contents

Contents

1. System composition

P

2. Functions performed by the system

P

3. CMB Controller

P

4. Remote control panel of MPC

P

5. Description of system operation

P

6. SMS - Features

P

7. Service

P

8. SIM card

P

Monitoring system of microclimate parameters and input voltage of the server room.

System composition

- monitoring panel of microclimate parameters and input voltage of the server room (hereinafter referred to as ShM);

- PDK2 remote control panel;

- temperature and humidity sensor.

Functions performed by the system

- Determination of deviation from the norm of parameters of the initial power supply.

- Recording of excess air temperature in the server room above the permissible limit.

- Setting of permissible limit of air temperature in the server room from the controller keyboard in ShM.

- Indication of monitored parameters and modes on the controller display in ShM.

- Sound and light indication of emergency modes on PDK2.

- Manual relief of power supply accident with PDK2.

- Permission/prohibition of audio signal operation in PDK2.

- Sending SMS about emergency situations and coming to the norm of controlled parameters to mobile phones of responsible persons.

- Reception of requests from phone numbers of responsible persons and sending of response SMS about status of controlled parameters.

CMB Controller

3.2. General description.

On the front panel of the controller there is a screen and control buttons. The purpose of the control buttons is shown in Figure 1. The controller has 2 work screens - main (screen 1) and setpoint input screen (screen 2). Screen 1 has no active control elements and is intended only for indication of main monitored parameters and status annunciator. Switching between work screens is carried out using the buttons for changing work screens. When you switch from screen 1 to screen 2, the setpoint input field becomes active as soon as the screen is switched. Set point is entered using 0-9 buttons. To remember the newly entered setpoint, press the temperature setpoint confirmation button. Clicking the "i" button will turn on the information screen of the installer. Pressing the "i" button again will switch to screen 1.

Remote control panel PDK2

On the front panel of the control panel there are light indicators and control elements. The purpose of the indicators and controls is shown in Figure 2. "System in operation" indicator is connected directly to ShM controller and signals about controller serviceability and algorithm operation. The "power failure" indicator lights up if the power supply parameters deviate from the norm and remains active until the power supply returns to normal and the power failure reset button is pressed. The power supply emergency release button is used for manual relief of power supply accident by the security officer. Pressing the button means confirmation of the elimination of the consequences of the power supply accident by the security officer. The system will not react in any way to pressing the button if the power supply parameters have not yet returned to normal or if the "Power supply accident" indicator is not lit. The audible signal is activated in case of any accident in the system (high temperature or power supply accident). The sound signal can be turned off using the sound control toggle switch.

Description of system operation

5.1. The main events that occur in the system.

5.1.1. The server room temperature is exceeded.

Once the room temperature reaches above the setpoint, the system triggers the following events:

- sending emergency SMS to numbers of responsible persons;

- actuation of emergency light and sound indication on PDK2;

- indication of the message "Accident" on a board of a condition of air temperature of the SM controller.

5.1.2. Return of air temperature to normal state after high temperature accident:

When the air temperature in the server is lower than the temperature setpoint - 1C, the system triggers the following events:

- sending SMS about temperature return to normal;

- shutdown of emergency light and sound alarm on PDK2;

- indication of "Normal" message on the annunciator of air temperature state of MT controller.

5.1.3. Recording by the system of deviation of parameters of controlled voltage from the norm:

- sending emergency SMS to numbers of responsible persons;

- actuation of emergency light and sound indication on PDK2;

- indication of "Emergency" message on the annunciator of MW controller power supply voltage state;

- indication of "Emergency" message on the alarm state annunciator of MW controller power supply.

5.1.4. Return of monitored voltage parameters to normal after power supply failure:

- sending SMS on return of parameters of controlled voltage to normal and on expectation of manual lifting of accident to numbers of responsible persons;

- indication of "Normal" message on the annunciator of MW controller power supply voltage state.

5.1.5. Manual confirmation (removal) of the power supply accident by the security officer after returning the power supply parameters to the norm :

- sending SMS about removal of accident by security to numbers of responsible persons;

- shutdown of emergency light and sound alarm on PDK2;

- indication of "Norma" message on the annunciator of MW controller power supply emergency state.

SMS - Features

The system receives and sends messages to the numbers of responsible persons on request and in case of control situations.

6.1. Messages sent by control situations to the numbers of all persons in charge.

6.1.1. Temperature exceeded message.

"Temperature in server room is XX.XC. It is higher than allowed limit YY.Y C. Datetime: zz.zz.zzzz zz: zz", where XX.X - the current temperature in server, YY.Y - the current setting of admissible temperature, zz.zz.zzzz zz: zz is current date.

Translation: Temperature in the server XX.XS. This is higher than the allowable limit YY.YC.

6.1.2. Report that the temperature is back to normal.

"Temperature in server room is normalized and equals XX.XC. It is less than alarm level YY.YC. Datetime: zz.zz.zzzz zz: zz", where where XX.X - the current temperature in server, YY.Y - the current setting of admissible temperature, zz.zz.zzzz zz: zz is current date.

Translation: The temperature in the server is back to normal and equal to XX.XS. This is less than the emergency limit YY.YC.

6.1.3. Occurrence of deviations of supply voltage parameters.

«Power supply alarm. Datetime: zz.zz.zzzz zz: zz, "where zz.zz.zzzz zz: zz is the current date.

Translation: Power failure.

6.1.4. Returns power settings to normal.

«Power supply is ok. Waiting for acknowledgement. Datetime: zz.zz.zzzz zz: zz, "where zz.zz.zzzz zz: zz is the current date.

Translation: The power settings have returned to normal. I expect the accident to be resolved.

6.1.5. Removal of power supply accident by security officer.

«Power supply alarm is acknowledged by security. Datetime: zz.zz.zzzz zz: zz, "where zz.zz.zzzz zz: zz is the current date.

Translation: Power accident removed by security officer.

6.2. Requests sent from the numbers of responsible persons to the ShM controller for information on the status of monitored parameters.

See Table 1 for the query text. For example, to obtain information about the monitored parameters, the subscriber with the 89161756928 number must send a message with the text Status5 to the controller number of the CMU. The text of the request message must be fully typed in the Latin layout. Only the subscriber who sent the request will receive a response to the request.

6.3. Messages on the status of monitored parameters sent by the ShM controller at the request of responsible persons.

«Temperature=XX.XC, temperature high limit=YY.YC, humidity=WW.W%, power supply is normal, power supply alarm is acknowledged. Datetime: zz.zz.zzzz zz: zz, "where XX.XC is the current temperature, YY.YC is the current set point of the permissible temperature, WW.W% is the current humidity, zz.zz.zzzz zz: zz is the current date.

Translation: Temperature = XX.XC, allowable temperature setpoint = YY.YC, humidity = WW.W%, power supply voltage is normal, power supply accident is removed.

Depending on the situation at the site, the following parts of the message may vary:

- temperature (XX.XC)

- current allowable temperature setpoint (YY.YC)

- Humidity (WW.W%)

- supply voltage (is normal or IN ALARM)

- Power failure (is acknowledged or not acknowledged)

Service

7.1. Batteries.

The ShM includes two standard acid-lead sealed batteries with a voltage of 12V and a capacity of 7A * h each. According to existing regulations, the recommended battery life is 2 years, regardless of the mode of operation .

Replacement of batteries must be carried out when the panel is powered off. The battery replacement procedure includes the following steps:

a) disconnect the batteries (push the button to start the batteries);

b) turn off the circuit breaker of the board power supply;

c) switch off the controlled voltage circuit breaker;

d) open the cover of the panel section with the controller;

e) remove terminals from batteries;

e) replace batteries;

g) connect terminals to new batteries;

h) to close a cover;

and) switch on the controlled voltage circuit breaker;

k) switch on the circuit breaker of the board power supply;

l) connect the batteries (press the button to start the batteries).

7.2. Check of SIM card balance.

The speed of spending on the SIM-card of the MCS board depends on the operating modes and the number of requests sent to the controller by the responsible persons.

The balance check interval is selected by the maintenance personnel depending on the above conditions.

Balance check procedure:

a) disconnect the batteries (push the button to start the batteries);

b) turn off the circuit breaker of the board power supply;

c) switch off the controlled voltage circuit breaker;

d) open the cover of the lower section ;

e) remove Siemens GSM modem from the din-rake;

f) pull out the SIM card. The slot with the SIM card is at the bottom of the modem. To open the slot, press a thin object on the yellow button next to the slot;

g) insert the SIM card into the phone and check the balance (* 100 # for MTS);

h) to insert the Sim card into the modem and to close a board cover;

and) switch on the controlled voltage circuit breaker;

k) switch on the circuit breaker of the board power supply;

l) connect the batteries (press the button to start the batteries);

7.3. Check of power supply of shield after power supply accidents.

For some types of mains failures, the following events may occur:

- disconnection of the circuit breaker for power supply of the switchboard located in the switchboard;

- disconnection of the switchboard circuit breaker located in the switchboard;

- overburning of fuse of module G1 of MCC board;

- overburning of the fuse of the power supply unit of the switchboard.

If one of these events occurs as a result of the power failure and the power check is not performed, the system can continue to operate for several more hours from the batteries, but after the battery capacity expires, it will be turned off.

7.3.1. Procedure for checking power supply after mains failures.

- check the circuit breakers in the switchboard and in the switchboard;

- measure the voltage on the red conductor L connected to one of the terminals "mains" of the G2 unit with an indicator screwdriver.

- visually check integrity of fuses of G1 unit;

- pull out of the socket and check the integrity of the accumulator fuse (the fuse is attached to the wall of the box above the G2 unit).

SIM card

The MTS operator SIM card with the following parameters is installed in the GSM modem of the shield board:

Phone number: 8-917--------------

PIN _________________

PUK ________________

Card registered on ______________________________

Tariff ___________________

Drawings content

icon схемы.dwg

схемы.dwg

Free downloading for today

Update after: 11 hours 21 minutes
up Up