Installation of cups for natural ventilation of Power Center

  • Added: 03.07.2014
  • Size: 317 KB
  • Downloads: 0
Find out how to download this material

Description

WDP focuses on scaffolding

Project's Content

icon
icon ППР Стаканы ЕС.dwg
icon ППР Стаканы ЕС 29.08.2013.doc

Additional information

Contents

2. GENERAL DATA

3. INSTRUCTIONS FOR DRILLING OF HOLES WITH DIAMOND TOOLS

4. GUIDELINES FOR THE INSTALLATION OF FRAME SCAFFOLDING

5. REQUIREMENTS FOR QUALITY AND ACCEPTANCE OF WORKS

6. OCCUPATIONAL SAFETY REQUIREMENTS

7. FIRE SAFETY REQUIREMENTS

8. ENVIRONMENTAL PROTECTION

9. FAMILIARIZATION SHEET

10. LIST OF REGULATORY AND TECHNICAL LITERATURE USED

GRAPHIC PART:

SHEET 1, 2: PROCESS FLOW CHARTS

ATTACHMENTS:

HEAT CIRCUIT HEATING ACTION SHEET

COST ESTIMATE FOR THE SUPPLY OF VOLCANO EQUIPMENT

HEAT GUN DEMAND SCHEDULE (CALCULATION)

CALENDAR PLAN

2. general data

1. This project was developed for the period of installation of natural ventilation glasses at the Energy Center during the construction of the corporate university of Sberbank of Russia at the address: Moscow Region, Istra District, Obushkovsky Rural District.

2. When tying this PDP to the Power Center housing, on which operations will be performed, look, given PDP, together with the PDP building plan, for construction of this housing.

3. instructions for drilling of holes with diamond tools

1. Prior to drilling, the following work shall be carried out: tool-driven axis splitting and hole dimensions (diameter and depth in mm) shall be determined; water and electric power are supplied to drilling zone; serviceability of the drilling unit was checked and its maintenance was carried out; the type of diamond drill is selected; radial run-out of installation spindle and drill is checked.

2. A diamond ring drill is used to drill holes, which is fixed on the spindle of the drilling unit. Under the action of axial pressure and rotational force created by the drilling unit, the cutting part of the drill is embedded in the drilled material. To cool the tool and take the broken material out of the bottom hole, water is supplied from the main pipe. The drilled core is removed from the face after drilling. Drill depth up to 400 mm, hole diameter from 20 to 160 mm.

The use of diamond tools in drilling allows you to obtain holes with high accuracy diameter without creating shocks and vibration; drill various materials without disturbing their structure;

expedite the preparation of design documentation by freeing designers from marking holes and openings;

improve working conditions, reduce dust content of working rooms, significantly reduce noise and vibration (compared with the use of punching hammers and other tools).

2.3. Diamond drilling is performed in the following process order:

by means of a feeding mechanism, the drill is brought to the treated surface at a distance of 10-15 mm and installed along the hole marking;

the valve is opened and in the initial drilling process the optimal water supply mode is set (the water flow rate depending on the drill diameter can be from 3 to 20 l/min);

electric motor is turned on and diamond tool is smoothly fed into processed material by means of feeding mechanism.

During drilling, care must be taken to ensure that the feed force does not exceed the amount at which the tool may be jammed. When the water supply or outflow is stopped, immediately remove the drill, shut down the engine and find out the cause of the failure and eliminate it.

When drilling sections with fittings, it is necessary to reduce the feed force in order to avoid breakage of the cutting part of the drill and engine overload; when sparks appear from the bottomhole, it is necessary to sharply reduce the supply force and increase the supply of water for cooling.

If the drilling speed is uneven and the drilling is accompanied by shocks, partial jamming, excessive heating of the drill, the sign of which is steam generation, the axial pressure and rotation speed should be reduced. When the drill is jammed into the bottomhole with broken material, immediately shut down the engine and turn the drill with a wrench several times without supplying water, then rotate the drill and slowly lift and lower it several times (extend or push it), and then continue drilling.

3. When drilling through holes in the slabs, it is necessary to reduce the axial pressure before the drill is released from the opposite side to prevent surface chipping and limit the free stroke of the drill.

4. At the end of drilling, the tool must be carefully removed from the bottomhole without turning off the electric motor and water supply, and then cut off the engine and water supply. The core is removed from the drill by its own mass. In this case, the core drop zone must be protected on the underlying floor and signal signs installed.

5. In case of blind drilling, the core is removed from the well by preliminary clogging of the metal wedge, peeling off the core from its base and removal from the well with special ticks. The gripping part of the ticks must correspond to the outer diameter of the core.

4. Guidelines for the Installation of Frame Scaffolding

1. This section is designed for installation and operation of frame scaffolding on the housing floors intended for drilling holes in the floor and installation of ventilation cups.

2. Stability of scaffolding in transverse direction is ensured by attachment of scaffold posts at the level of joints to building elements with inventory plugs, and in longitudinal direction stability is ensured by setting diagonal connections along external row of posts.

3. Forests are installed on floors to a height of up to 4 m.

4. The working floor on the side of the outer row of scaffolding shall have a fence. The height of the fence must be not less than 1.1 m, the side element must be not less than 0.15 m, the distance between the horizontal elements of the fence must be not more than 0.5 m.

5. The installation and dismantling of frame scaffolding can only be carried out by persons who have full technical knowledge in this area.

6. Scaffolding shall be equipped with stairs for lifting and lowering people in each 16 scaffolding block.

Installation of scaffolding.

7. Prior to commencement of erection work:

- install temporary barriers along the boundary of the hazardous area for the period of installation, operation and dismantling of scaffolding. The value of the hazardous area is accepted in accordance with Appendix "D" SNiP 12032001 "Occupational safety in construction. Part 1. Basic requirements ";

- deliver to the installation site repaired, sorted and complete according to the specification of scaffold elements;

- prior to erection of scaffolding, the erection manager shall carefully inspect each element and parts of scaffolding to determine their quality and suitability for erection.

8. Perform installation and removal of scaffolding by a link of fitters and fitters consisting of 4 people:

4p. - 1 person.

3p. - 2 people.

2p. - 1 person.

9. Work in daylight, in one shift.

10. When erecting scaffolding, strictly observe the sequence of erection of scaffolding and ensuring its stability. At the same time pay special attention to:

- on the quality of the base under the stands of forests. Install struts on distribution linings from boards h = 40mm with attachment of spindle of supports of scaffold struts after installation of the 1st tier of scaffolding;

- for correct alternation of forest anchoring elements;

- on vertical position of the established racks of the woods (racks of the woods are established on a plumb);

- for installation of scaffolding;

- for tightening of nuts on folding bolts of clamps according to DIN EN 74 standards, which prevent their slipping. Sufficiency of tightening is checked by test wrapping of nuts with wrench for shutoff;

- installation of working flooring and board fences on working flooring;

- to the installation of Alunastilles with a passage (with a hinged cover) and stairs, which are mounted so that the stairs are alternately left and right in different blocks of scaffolding. The lowest staircase rests on the flooring, which is hung on the support bundle;

- the floorings shall be held horizontally on the transverse projections of the bolts and fixed at right angles to the facade or parallel.

11. The scaffolding shall be installed under the supervision of the works manufacturer. The Works Manufacturer shall:

- Carefully familiarize yourself with the forest design;

- accept the set of scaffolding according to the specification, with rejection of damaged elements;

- instruct workers on safe working methods, procedures and techniques for erection of scaffolding and their attachment to load-bearing elements of the building;

- check the availability of tolerances for workers who allow them to perform work at altitude.

Acceptance and operation of scaffolding .

12. Installed scaffolding with a height of more than 4 m is accepted by the commission, installed scaffolding with a height of up to 4 m is allowed for operation only after their acceptance by the manufacturer or the foreman and registration in the work log. The commission and its composition are appointed by order of the construction and installation department. The mandatory member of the commission is the responsible representative of the SMU responsible for safety. The visor and scaffolding shall be deemed accepted for operation after the commission has issued the relevant act and approved it by the General Director .

13. Each workplace on the forests adjacent to the building or structure must be protected from above by a scaffold located at a distance of not more than 2 m in height from the working scaffold.

14. When the scaffolding is put into operation, the following shall be checked:

- presence of bonds and fasteners ensuring stability;

- attachment units of individual elements;

- reliability of support platforms and grounding.

15. The condition of joints and fixtures of forests during their operation should be systematically monitored, for which purpose a person responsible for supervision of forests is appointed by the order of the construction department.

16. The condition of the scaffolding must be checked daily before the start of the shift by the work manufacturer or the supervisor.

17. Scaffolding and stairs of forests should be systematically cleaned of debris, remnants of materials.

18. Perform work from only one scaffold. It is strictly forbidden to perform works simultaneously from several levels of forests along the same vertical.

19. It is strictly forbidden to remove anchors and scaffolding during work.

20. Supply materials to scaffolding in tiers by hand.

Dismantling of scaffolding.

21. Removal of scaffolding is allowed only after completion of all works with them and after garbage removal, remnants of materials, as well as equipment and tools from the flooring of the protective visor and scaffolding.

22. Prior to dismantling of scaffolding, the works manufacturer shall inspect them and instruct the workers on the sequence and methods of disassembly, as well as on measures ensuring safety of the works.

23. Demolition of scaffolding shall be started from the upper tier and carried out from top to bottom in the following order:

- remove the railings of the fence;

- remove struts, joints of which coincide with disassembled tier;

- remove scaffolding;

- remove the fasteners to the wall;

- disassemble the stair sections of the scaffolding simultaneously with the forests to which they adjoin.

5. requirements for quality and acceptance of works

1. The required quality and reliability of scaffolding installation and operation shall be ensured by construction organizations by implementing a set of technical and organizational measures in accordance with the requirements of GOST 2732187 "Rack-side scaffolding for construction and installation works-bot," SNiP 12012004 "Construction organization."

2. Production quality control of scaffolding shall include incoming quality control of scaffolding elements, operational control of individual installation processes or operations and assessment of compliance of installed scaffolding.

3. During incoming inspection of scaffold elements, their completeness and compliance with the requirements of the standards is checked, as well as the availability and content of passports, certificates and other accompanying documents. The results of incoming control are recorded in the "Log of incoming accounting and quality control of the obtained parts, materials, structures and equipment."

4. Each lot of scaffolding consisting of a set of elements is sent to the consumer in package and is accompanied by the manufacturer's certificate, the acceptance certificate of the OTC and the pick specification, which indicates the number and mass of the sent elements by marks.

5. Large scaffold parts are sent from the manufacturer without packaging, bound by wire in bundles weighing not more than 80 kg. A tag indicating the mark and number of elements in the pack is attached to each packet.

6. Elements of forests, sorted by grades, are stored in closed rooms or outdoors on linings under a canopy, without contacting the ground. Preservation is performed in accordance with GOST 1316367 *.

7. Before being sent to an object, forests are complete with all typical and non-typical elements according to the project specification of the forest of a particular object. Scaffolding is carried out with rejection of elements of scaffolding that do not meet normative tolerances.

8. When picking scaffolding, the following standard pre-start and requirements are met:

- all elements of scaffolding, including steel flooring, handrails, side boards, shall be treated with fire retardant;

- geometric dimensions of steel flooring, stairs and other elements shall correspond to the design;

- deviations from design length of scaffold elements shall not exceed in verticals + 2 mm, and in other elements ± 3 mm.

9. Transportation of scaffolding is performed by transport of any type ensuring preservation of elements of scaffolding from damage.

It is not allowed to drop articles during unloading, transportation by fiber and other actions that can cause damage to structural elements.

During transportation and storage, bags and boxes can be stacked on top of each other in no more than three tiers.

Scaffolding elements shall be stored in closed rooms or under a canopy on linings excluding contact with soil.

10. During operational control, compliance with the technology of erection of scaffold elements, compliance of scaffold installation with working drawings, construction codes, rules and standards is checked.

11. When assessing conformity, the required quality of the installed scaffolding prepared for operation is checked.

12. Metal tubular scaffolds of wedge type are allowed for operation only after the complete completion of their installation, acceptance by the commission with the participation of persons responsible for installation of scaffolding, work from scaffolding, as well as the person responsible for labor protection in the organization and registration by act.

13. At acceptance of installed scaffolding for operation the following are checked:

- setting the level of scaffolding on a rigid base and reliability of support platforms;

- compliance of assembled frame with installation diagrams;

- correct assembly of units (correct installation of verticals, reliable connection of contour locks and diagonals with vertical flanges, installation of contours and diagonals in the required set) and compliance of scaffolding attachment with the design;

- correctness and reliability of forest support on the base;

- presence and correctness of fencing, flooring and stairs installation and attachment;

- presence of diagonal connections along the outer row of posts;

- safeguarding the forests against possible vehicle strikes;

- Ensuring the removal of water from forests;

- verticality of verticals installation and availability of scaffolding attachment to walls;

- correct installation of lightning receptors and grounding device;

- availability of fire extinguishing equipment;

- scaffolding acceptance shall be performed under design load located on working floor of upper tier. The value of the load and its location should correspond to the load scheme adopted in the design of the scaffolding.

14. Reliability of attachment is checked by accessory for control of forces of forest plugs jamming, which develops pulling force of at least 300 kgf.

When pulling force of 300 kgf is applied to the plug, it must not be pulled out of the wall.

15. The surface of the soil on which forests are installed must be planned, sealed and surface water removed from it.

16. During operation, the condition of all joints, wall anchorages, floorings and fences shall be monitored systematically. To do this, every day before the start of the shift, the forests are inspected by the foreman or master of the leadership work performed from these forests.

At least once every 10 days, the condition of the scaffolding should be checked by representatives of the construction organization with a record of defects noticed.

17. In all cases of detection of deformations of elements of forests, disturbance of stability and other defects, work from forests should be stopped before correction and re-acceptance of forests.