Work Design - Automatic Fire Fighting Installation

  • Added: 14.08.2014
  • Size: 562 KB
  • Downloads: 1
Find out how to download this material

Description

To be protected: hand-painted chambers - 3 pcs., drying chamber, paint preparation box

• manual painting chambers - 3 pcs. Dimensions 1.5 * 1.2 * 2m. The area of each chamber is 1.8m2, the volume is 3.6m3.

Project's Content

icon
icon
icon
icon
icon Cх общ Черноголовка.dwg
icon Окрас. камера.dwg
icon ПЗ _камера.doc
icon спец.Черногол.dwg

Additional information

Contents

CONTENTS

1. General part

2. Purpose, composition and main characteristics of automatic

powder fire extinguishing units

3. Characteristics of protected premises

4. Calculation of quantity of powder fire extinguishing modules

5. Main technical solutions adopted in the project

6. Information on organization and maintenance of installation works

Power supply and earthing

7. Health and safety measures

8. Maintenance and maintenance of automatic installation

fire extinguishing

Appendix: Tasks to the Customer

1. common part

The following are protected: manual painting chambers - 3 pcs., drying chamber, paint preparation box.

Modular type AUPP, fire extinguishing agent - powder.

AUPP is made on the basis of modules of powder MPP100.07

TU 48540051177 6979-01. Fire safety certificate

NSSPB.RU.UP001.B02372, Certificate of Conformity

NPOCC.RU.BB02.H01261. Explosion Protection Certificate

CS RE IGD N99.S157 (marking of explosion protection 2ExdIICT3X).

The technical solutions adopted in the project meet the requirements of the following regulatory documents:

GOST R 5109197. Powder fire extinguishing units are automatic. Types and basic parameters.

NPB-88-01. Fire fighting and alarm systems. Design Codes and Regulations.

NPB-104-95. Design of fire warning systems for people in buildings and structures.

NPB-110-99. List of buildings, structures, premises and equipment to be protected by automatic fire fighting and detection units.

PUE-98. Electrical Installation Rules.

SNiP 2.08.0289. Public buildings and structures.

SNiP 3.05.0584. Process equipment and process pipelines.

PPB-01-98. Fire safety rules in the Russian Federation.

RD 25.95390. Automatic fire extinguishing, fire and fire alarm system. Symbols and schematic graphical links.

RD 25.96490. System for maintenance and repair of automatic fire extinguishing, smoke removal, fire and fire alarm systems. Organization and procedure of works.

RD 78.14593. Systems and complexes of security, fire and fire alarm. Rules for production and acceptance of works.

RD 0090196. Fire automation units. Technical Content Rules.

VSN 25.09.6785. Rules for production and acceptance of works. Automatic fire extinguishing units.

1.6. All instruments and devices used have a certificate of conformity and fire safety.

1.7. The equipment, which is part of APCP, when placed in explosive areas, has an explosion-proof design.

Purpose, composition and main characteristics of the automatic powder fire extinguishing unit

2.1. APCP is designed for automatic detection and extinguishing of fire centers when the controlled fire factors exceed the established threshold values in the protected area. The CPA also notifies the facility personnel and/or fire department about the fire.

2.2. The APCP consists of:

powder fire extinguishing module MPP10007 3 pcs.

powder supply lines, set 3

cable network

equipment for automatic fire detection and starting of modules based on "Dozor16" PPKOP

"Output" annunciator - 3 pcs;

"Leave powder" annunciator - 3 pcs.;

thermal fire detector IP 1034/1IB 16 pcs.;

fire flame detector Pulsar 2012 4 pcs.;

fire detector manual IPR -3SU 3 pcs;

device for manual electrical starting of URP7 3 pcs.

device for galvanic isolation and provision

"intrinsic safety" of a loop UPKOP of 13511 4 pieces.

2.4. Automatic fire detection and start-up equipment of modules based on "Dozor16" PPKOP is designed to build and monitor the status of alarm loops and start-up circuits, generate indication control signals and external devices, and output starting pulses to fire extinguishing modules.

Characteristics of protected premises

3.1. The following shall be protected:

manual painting chambers - 3 pcs. Dimensions 1.5 * 1.2 * 2m. The area of each chamber is 1.8m2, the volume is 3.6m3. Classification of an explosive zone by PUE - V-1a

paint preparation area, area 15 m2, volume 60m3. Classification of an explosive zone by PUE - V-1a

thermal radiation drying chamber, dimensions 10 * 1.5 * 2m. Possible temperature range 80180so. Classification of explosive area according to PUE - V-1b.

Classification of explosive zone by PUE within a radius of 5 m from open openings of all chambers - V-1b.

Main technical solutions adopted in the project

5.1. In automatic mode PPKOP "Dozor16" performs constant cyclic polling of connected devices, analyzes the status of alarm loops and start-up circuits.

5.2. Loops passing through controlled zones (2 loops each in the zone) are logically combined into fire extinguishing directions:

drying chamber thermal radiation - direction 1

paint chambers - direction 2

paint preparation area - direction 3.

5.3. When laying alarm loops through explosive areas, the CPCP 13511 device provides galvanic isolation of the loops and the type of explosion protection "intrinsically safe circuit."

5.4. In one of 2 alarm loops of each direction, a manual fire detector is included to manually generate the "Attention" signal in this direction.

5.5. At actuation of one fire detector in alarm loop the control equipment of automatic control system generates signal "Attention" with indication of direction in which actuation occurred. Sonic and light annunciators of PPKOP "Dozor16" are switched on. The signal "Attention" is transmitted to the PCP and/or the fire department room of the enterprise.

5.6. When two fire detectors operate in different loops of the same fire extinguishing direction, the control equipment enters the "Fire" state. "Leave powder" light-and-sound annunciator of this direction is ON. Commands for disconnection of supply units and de-energizing of process equipment are generated. If the automatic control system is in the "Automatic on" state, a thirty-second count of the delay in the release of the fire extinguishing agent (the time required to evacuate people) begins.

5.7. Upon completion of thirty-second delay of PPKOP "Dozor16" outputs electric pulse to starting device MPP100.07 of direction in which detectors were activated, opening of membrane occurs, working gas is supplied from cylinder to module housing. After increasing the pressure in the housing to the operating value, the membrane is opened and the fire-extinguishing powder in a fluidized state enters the distribution pipeline and then through the sprayers to the protected area.

5.8. The modules for each fire-fighting direction can also be started manually from PPKOP "Dozor16" or from the manual starting device of URP7.

Attention! Starting from URP7 is performed without delay.

5.9. On the doors to the protected rooms there are contact detectors that turn off the automatic start of the installation when they open. Indication of disabled state is displayed on "Automatic ON" annunciator located in front of inputs to protected rooms.

5.10. Automatic start mode is restored by introduction of code from PKP16 or from monitoring panel of BPN PPKOP "Dozor16."

5.11. Given the presence of high temperatures in the drying thermal radiation chamber and at the request of the customer, explosion-proof fire detectors "Pulsar 2012" are used to detect possible fire centers in the chamber.

5.12. The design of fire extinguishing plants completely eliminates the possibility of the fire extinguishing agent entering the protected room before the plants are activated, which guarantees the safety of personnel in these rooms.

5.13. Fire extinguishing powder by the degree of exposure to the body refers to low-hazard substances of hazard class IY in accordance with GOST 12.1.00776. Irritating effect: on the mucous membrane of the eyes - weakly expressed, on the skin - absent. Powder compositions used are not toxic, do not corrode metals in dry form. After a fire, the powder can be removed with a vacuum cleaner or washed away with water.

Information on organization and maintenance of installation works. power supply and earthing

6.1. Installation of the powder fire extinguishing module is recommended in the following sequence: preparatory work, measurements of the protected room, binding and installation of the module.

6.2. Piping shall be laid with a slope of at least 1:100 towards the sprayers.

The distance from the nozzles to the attachment unit of the corresponding pipeline is not more than 0.5 m. The distance between the pipe attachment elements must be not more than 3 m.

6.3. Install the pipelines using clamps and on site, in accordance with the placement plans, coordinating the attachment places with the site administration.

6.4. Steel water and gas pipes GOST 326275 shall be used for the pipeline.

6.5. Wires and cables shall be laid in accordance with PUE, NPB 8801.

The circuits of alarm loops shall be laid along the walls and ceiling in 20x10 ducts or corrugated pipe of non-combustible ∅16, install by wire of KSPV 2x0.5 mm type.

Start-up and warning circuits shall be laid by 2x0.75 mm2 PVC wire in corrugated pipe ∅16. Start-up and alarm circuits can be laid together in one corrugated pipe.

6.6. In all cases where wires and cables pass through walls, wire or cable, lay in a separate piece of steel pipe.

6.7. The distance between the fire-fighting communication systems by cables and power cables shall not be less than 0.25 m.

Power supply and earthing

The fire alarm system shall have category I power supply according to PUE. If it is impossible to supply electric receivers from two independent sources, it is allowed to supply them from one source: from different transformers of two-transformer or from two nearby single-transformer substations connected to different supply lines laid along different routes with an automatic reserve input device.

Earthing of modules tanks shall be performed by wire with copper core section not less than 1.5 sq. mm. Connect all grounding wires to the common grounding circuit of the building, refer to RD 78.14593. Operation of the device should be carried out in accordance with the "Rules for technical operation of electrical installations by the consumer" and "Intersectoral rules for labor protection (safety rules) during operation of electrical installations" put into effect with the 01.02.2001 of the State Energy Supervision.

Maintenance and maintenance of automatic fire extinguishing unit

At the facility, all types of work on maintenance and maintenance, as well as on the content of fire automation units, must be carried out by the facility's own specialists who have undergone appropriate training, or under an agreement with organizations licensed by the State Fire Service management bodies for the right to perform work on the installation, adjustment and maintenance of fire automation units .

The main purpose of maintenance is to carry out measures aimed at maintaining the units in a ready-for-use state: preventing faults and premature failure of component devices and elements.

The structure of maintenance and repair of modules includes the following types of works:

maintenance;

planned maintenance;

planned overhaul;

unscheduled repairs.

Observation of planned work of installation, elimination of the found defects, adjustment, control, approbation and check of integrity of chains of start of the elements gas-generating belongs to maintenance.

The scope of maintenance includes partial disassembly, replacement or repair of the module. Measurements and tests of equipment and elimination of detected defects are carried out.

The scope of overhaul, in addition to the work provided for by the current repair, includes the replacement of worn-out plant elements.

Unscheduled repairs are carried out in the scope of current or major repairs and are carried out after a fire, accident caused by unsatisfactory operation of the equipment, or to prevent it.

During maintenance works, the requirements of the "Instructions for the Organization and Performance of Works on Regulated Maintenance of Fire Fighting, Fire and Fire Alarm Plants," 1982, the Ministry of Internal Affairs of the USSR and the Ministry of Defense of the USSR, RD 78.14593, as well as RD 0090196 "Fire Automation Plants. Technical Content Rules. "

The 100% powder reserve for fire extinguishing modules in accordance with the maintenance contract is stored in STK "Flame" and delivered as required to the customer, as well as one-time devices URP7.

Typical maintenance schedule MPP100.07 is given in MPP100.000-07RE.

Task

for design of protective grounding of automatic powder fire extinguishing unit

Object: Area painted with liquid LMB

5-2002.AUP.Zd.1

Technical requirements for protective grounding of automatic powder fire extinguishing unit.

All metal parts of electrical equipment that are not normally energized, but which may be under it, due to insulation failure, shall be grounded.

Devices and panels of fire automation, modules, terminal boxes, pipes for wiring, electrical equipment cabinets shall be grounded. Protective grounding resistance shall not exceed 4.0 Ohm.

Grounding shall be performed in accordance with PUE, SNiP 3.05.0685, requirements of GOST 12.1.0387 and technical documentation of manufacturers.

The use of metal buildings, pipes as earthing, is allowed only as an additional measure.

Check grounding resistance (not more than 4 ohms) once every 3 years. Grounding circuit integrity check - 1 times a year.

Task

for laying of fire extinguishing modules starting circuits

Object: Area painted with liquid LMB

5-2002.AUP.Zd.2

Technical requirements for laying of fire extinguishing module start-up circuits.

Lay fire extinguishing modules starting circuits in corrugated non-combustible pipe.

Distance between cables and electrical communications, pipelines with combustible gases shall be not less than 0.5 m.

In all cases where wires and cables pass through walls, wire or cable, lay in a separate piece of steel pipe.

Emergency lighting shall be provided at the location of the manual start-up device, which shall provide illumination of at least 10% of the operating lighting standard 100150 lux.

Task

for power supply design of automatic powder fire extinguishing unit

Object: Area painted with liquid LMB

5-2002.AUP.Zd.3

Technical requirements for power supply of the automatic powder fire extinguishing unit.

According to the degree of reliability of power supply, fire extinguishing plants are consumers of category 1 with voltage of 220 V, frequency of 50 Hz, power of at least 0.5 kW.

Operating input as per MV 17475 p.1114.

To carry out all works on check, control, adjustment of the equipment at the disconnected EGP chains.

Drawings content

icon Cх общ Черноголовка.dwg

Cх общ Черноголовка.dwg

icon Окрас. камера.dwg

Окрас. камера.dwg

icon спец.Черногол.dwg

спец.Черногол.dwg

Free downloading for today

Update after: 9 hours 47 minutes
up Up