Overhaul of RVS-1000 m No. 1 at UPPN Shuma TsDNG-9
- Added: 01.07.2014
- Size: 7 MB
- Downloads: 4
Description
Project's Content
|
|
10 схема3.cdw
|
22 .1 Стройгенплан.cdw
|
22 Стройгенплан.cdw
|
24.1 Патрубок Ду 500 в крыше.cdw
|
24.2 Площадки и огр_на крыше_ разрезы.cdw
|
24.3 Элемент кольцевого перехода ЭПК-1.cdw
|
25.1 ЛШ ограждения.cdw
|
25.2. Крепление ЛШ к стенке.cdw
|
25.3 Мостик переходный огражд..cdw
|
26.1 Первый пояс.cdw
|
26.2 Строповка листа стенки.cdw
|
26.3 л.Патруб. в стен. Ду25.cdw
|
26.4.Патруб. в стен. Ду50.cdw
|
26.5 Патруб. в стен. Ду100.cdw
|
26.6 Патрубок Ду 150 в стенке.cdw
|
26.7 Патрубок Ду 200 в стенки.cdw
|
26.8 ЛЛ500.cdw
|
26.9 ЛЛ 600х900.cdw
|
27.1 пробоотборник.cdw
|
27.2 корыто пробоотборник.cdw
|
28.1.1 Спецплощадки ПГ.cdw
|
28.1.площадка пеногенератора.cdw
|
28.2.1 Спец стремянки ПГ.cdw
|
28.2.стрем.пеноген.cdw
|
28.3.Фланец пеногенератора.cdw
|
29 Днище.cdw
|
30 ПОЗ.cdw
|
44-1 Стенка.doc
|
44-2 Стенка-Днище.doc
|
44-3 Трубы.doc
|
8 схема1.cdw
|
9 схема2.cdw
|
Автокран КС-54711-1.doc
|
Антикор внутр.план.cdw
|
Антикор наруж.план.cdw
|
ППР-52.doc
|
РВС-1.cdw
|
РВС.doc
|
Титульный РВС.doc
|
ТК 52-2 Шумы наружное АКЗ.doc
|
ТК 52.1 Шумы внутреннее АКЗ.doc
|
Additional information
Contents
1. General requirements
2. Stroygenplan
3. Lifting mechanisms and equipment used
4. List of lifting loads and removable load grippers
5. Performance of works
6. Safety requirements
7. Environmental protection activities
8. Accident Response Plan
9. Evaluation Sheet
Appendix A. Stroygenplan
Appendix B. Technical characteristics of cranes
Appendix B. Tank roof
Mine ladder
Tank wall
Internal filling
GPSS sites
Tank bottom
Gate valve maintenance area
Appendix G. Routings
For welding of wall sheets
For welding of wall and bottom
For welding of pipe joints
For PBC test
Internal CPS
External CPS
Appendix D. Work Schedule
Appendix E. Cargo slinging diagrams
Appendix J. Tour construction. Order and Typical Assembly Diagrams
2. Stroygenplan
2.1. Refer to Appendix A. Final layout of equipment to be agreed with UPPN management.
3. Lifting mechanisms and equipment used
3.1. Use crane KS547111, (technical specifications see Annex B) or other crane with similar technical specifications for unloading, dismantling and erection of tank steel structures.
3.2. It is allowed to use ground and manual suspension mounting winches, scaffolds of corresponding lifting capacity, both inside the tank and outside.
5. Performance of works
5.1. General requirements
5.1.1. Work shall be carried out in accordance with the following regulatory and technical documentation:
- SNiP 12012004 "Construction Organization";
- SNiP 3.02.0187 "Earthworks, foundations and foundations";
- SNiP 3.04.0385 "Protection of building structures and structures against corrosion";
- SNiP 3.05.0584 "Process equipment and process pipelines";
- GOST R 529102008 "Vertical cylindrical steel tanks for oil and oil products";
- PB 0360503 "Rules for arrangement of vertical cylindrical steel tanks for oil and oil products";
- VSN 31189 "Installation of steel vertical cylindrical tanks for storage of oil and oil products with volume from 100 to 50000 m3."
- RD 010022003 "Procedure for operation, maintenance and repair of vertical steel tanks in subsidiaries of OAO LUKOIL"
- RD 089595 "Regulation on technical diagnostics of welded vertical cylindrical tanks for oil and oil products."
- PB 0358503 "Rules for arrangement and safe operation of process pipelines";
- PB 1038200 "Rules for arrangement and safe operation of lifting cranes";
- "Production instruction for crane operators (drivers) on safe operation of boom self-propelled cranes (automobile, caterpillar and pneumatic wheelers)";
- "Production instruction for rafters on safe handling of lifting mechanisms."
5.1.2. The number of rafters is 2 people per shift. When lifting and moving loads, use braces.
5.1.3. Erection works shall be carried out in daytime from 800 to 1700
5.1.4. It is forbidden to move goods by cranes over existing production rooms and equipment.
5.1.5. All workers employed at the construction site must be trained in safe working methods by profession and type of work, certified and have certificates with them.
5.2. Work Sequence
5.2.1. Preparatory work
5.2.1.1. Prior to the start of the tank repair work, it is necessary to prepare platforms for the operation of lifting equipment, storage of materials and products.
5.2.1.2. Install a strong crossing through the pipeline underpass in the tank frame, for the passage of GPM and trucks.
5.2.2. Installation of cranes
5.2.2.1. Install cranes for installation of equipment, piping units and steel structures in accordance with Appendix B.
5.2.2.2. Install boom crane on cleaned, planned and tamped site (with inclination angle not more than 3 °), taking into account soil category and nature and with drainage.
It is not allowed to install a crane for operation on freshly assimilated undiminished soil, as well as on a site with a slope exceeding the one specified in the certificate. Strong and stable linings shall be laid under the remote supports. Linings for additional supports of the crane shall be its inventory.
During operation, monitor the soil condition to avoid subsidence.
5.2.2.3. Cranes shall be installed in such a way that when lifting the load, it is not necessary to carry it in advance at the inclined position of the cargo ropes and it is possible to move the load, raised not less than 500 mm higher than the equipment encountered in the path, stacks of cargo, sides of rolling stock, etc., as well as during operation the distance between the turning part of the crane at any position and buildings, stacks of cargo and other objects were not less than 1000 mm.
5.2.3. Repair of the mine ladder.
5.2.3.1. Mount the stand-alone shaft ladder. Maintain the distance between the supporting attachment plates and the welded seams of the tank wall:
vertical - not less than 250 mm;
horizontal - not less than 100 mm.
5.2.3.2. Remove railings of stairways and intermediate platforms of shaft ladder.
5.2.3.3. Install new railings of stairways and intermediate platforms that meet the requirements of the technical documentation:
5.2.3.4. Grind all welds from slag and splash.
5.2.3.5. Repair the base of the mine ladder, for this it is necessary to fill it with concrete mortar.
5.2.4. Repair of tank roof.
5.2.4.1. To dismantle a branch pipe of Du500 on a tank roof;
5.2.4.2. Fabricate and install a new reinforcing pad on the tank roof together with the nozzle DN 500;
5.2.4.3. Check welded joints during vacuum tests of the tank, by soap - 100%;
5.2.4.4. Dismantle maintenance platforms on the RVS roof, using gas and machine cutting;
5.2.4.5. Manufacture new ring passages and install them together with old ones on the tank roof, close to the fences, according to the requirements of item 3.13.3 of PB 0360503 (the height of the fences from the platform floor to the top of the railings must be at least 1250mm .)
5.2.5. Repair of foam generator platforms.
5.2.5.1. Remove old foam generators, service platform railings and stairs to them. Grind the places of welding of the removed structural elements flush with the main metal;
5.2.5.2. Manufacture and install new railings of foam generator service platforms. The fences shall be made in accordance with the requirements of cl.1.4.18. PB 0862403;
5.2.5.3. Cook the baseplates of the platforms along the contour.
5.2.5.4. Fabricate and install new tunnel-type ladders for lowering from the roof to foam generator service platforms. Perform ladders according to the requirements of para. 1.4.17. PB 0862403;
5.2.5.5. Fabricate and install guard gates;
5.2.5.6. Fabricate and install new flange connections of foam generators
5.2.5.7. Install new GPSS - 2000 - 2 pcs.
5.2.7. Tank bottom.
Repair the bottom together with replacement of parts of the first and second sheets of the first belt.
5.2.7.1. Install vertical mounting devices of 3 pcs. outside the tank, preventing wall subsidence in the area of the 1st sheet;
5.2.7.2. Mark and cut replaceable bottom sections:
mark the bottom sheets to be dismantled;
brace the tank wall in zone 1 of the sheet from the bottom;
cut out the dismantled sections of the bottom;
5.2.7.3. Remove the old hydrophobic layer under the repair site;
5.2.7.4. Lay a new hydrophobic layer of sand mixed with spent oil, followed by compaction, manually, to the design mark;
5.2.7.5. Install the bottom section:
prepare the bottom sheet installation site. Install assembly limiters;
lay the bottom sheet in the prepared place;
perform preparation of bottom sheet edges for welding;
fit butt with bottom sheets and attach to bottom. The length of the tacks is 2030 mm, the distance between the tacks is 4050 mm;
perform welding of the tank bottom sheet;
remove mounting devices and grind places of welds flush with base metal;
other bottom sheets are welded in a similar manner;
leveling the protruding part of the bottom, if necessary, knock out the hydrophobic mixture;
prepare the edges of the welding wall sheet;
fit butt with bottom sheets and attach to bottom. The length of the tacks is 5060 mm, the distance between the tacks is 400500 mm;
welding the wall sheet to the bottom of the tank;
remove mounting devices and grind places of welds;
5.2.7.6. Perform quality control of welds:
visual-measuring - 100%;
radiographic - 100% of welded joints of the bottom in the area of the wall belt adjoining;
5.2.8. Other works.
5.2.8.1. Repair RVS windshield. Seal cracks and gaps in the pavement with bitumen. Perform graveling with concrete mortar, maintain the slope in accordance with the requirements of PB 0360503.
5.2.8.2. Perform revision of valves NDKM250 and KPG250 with issue of certificate.
5.2.8.3. Fabricate and install part (2 m) of the acceptance gate valve maintenance platform according to the requirements of PB 0862403, p. 1.4.18, 1.4.23, 1.4.16, 1.4.15:
excavate the pits for the foundations of the site supports;
leveling of foundation pits bottom under design elevation;
perform sand preparation for foundations b = 100 mm;
install foundation blocks for platform supports (2 pcs);
backfill the foundations;
install part of the site on the foundations and weld it to the existing site.
5.2.8.4. Remove the pipe from gate valve No. 4691 (2 m), install the flange blanking on this gate valve.
5.2.8.5. Cut temporary features on 5 1Tank Axis sheet. If necessary, weld the cutting places, with subsequent grinding flush.
5.2.9. Hydraulic testing of the tank
5.2.9.1. Overpressure test of the tank;
5.2.9.2. Tank vacuum test;
5.2.9.3. Measure deviations of tank generatrices from vertical and measure deviations of the external contour of the bottom from horizontal.
5.2.10. Corrosion protection
5.2.9.1. Apply the internal anticorrosive coating on the roof, wall, central stand, bottom, inner filling of the tank:
- installation of scaffolding and construction tour;
- sandblasting of all internal surfaces;
- dusting and degreasing of surfaces (immediately before painting);
- coating Intersel 670 on roof, wall, central stand in three layers;
- disassembly of tubular scaffolding and construction tour.
5.2.9.3. Painting the outer surface of the tank:
- arrangement of tubular scaffolding;
- provision of dusting and degreasing of repair places (immediately before painting);
- application of primer to repair sites;
- painting in 2 layers of repair places with Vinikor62 material;
- dusting and degreasing of the entire surface of the tank (immediately before painting);
- painting in 1 layer of the entire tank with Vinicor62 material;
- application of logos and symbols;
- disassembly of tubular scaffolding.
6.4. Fire Safety
6.4.1. It is not allowed to accumulate combustible substances on the sites, they should be stored in closed metal containers in a safe place.
6.4.2. Fire fighting equipment shall be maintained in serviceable, serviceable condition. The number of fire extinguishers shall be at least two at the workplace. Passages to fire fighting equipment shall always be free and marked with appropriate signs.
6.4.3. On construction machines and mechanisms running on liquid fuel, install spark arresters on exhaust systems.
10 схема3.cdw
22 .1 Стройгенплан.cdw
24.1 Патрубок Ду 500 в крыше.cdw
24.2 Площадки и огр_на крыше_ разрезы.cdw
24.3 Элемент кольцевого перехода ЭПК-1.cdw
25.1 ЛШ ограждения.cdw
25.2. Крепление ЛШ к стенке.cdw
25.3 Мостик переходный огражд..cdw
26.1 Первый пояс.cdw
26.2 Строповка листа стенки.cdw
26.3 л.Патруб. в стен. Ду25.cdw
26.4.Патруб. в стен. Ду50.cdw
26.5 Патруб. в стен. Ду100.cdw
26.6 Патрубок Ду 150 в стенке.cdw
26.7 Патрубок Ду 200 в стенки.cdw
26.9 ЛЛ 600х900.cdw
28.1.1 Спецплощадки ПГ.cdw
28.1.площадка пеногенератора.cdw
28.2.1 Спец стремянки ПГ.cdw
28.2.стрем.пеноген.cdw
28.3.Фланец пеногенератора.cdw
30 ПОЗ.cdw
8 схема1.cdw
9 схема2.cdw
Антикор внутр.план.cdw
Антикор наруж.план.cdw
РВС-1.cdw
Similar materials
- 26.01.2022
- 24.03.2024
Free downloading for today
Other materials
- 24.04.2014