• RU
  • icon Waiting For Moderation: 45
Menu

MCUD. Access Control and Control System

  • Added: 14.08.2014
  • Size: 2 MB
  • Downloads: 1
Find out how to download this material

Description

Project MCUD in the Data Processing Center Rostpromstroybank (OJSC) of Rostov. Access control and monitoring system for reliability of power supply belongs to electric receivers of the first category.

Project's Content

icon
icon
icon
icon 05_Пояснительная записка.doc
icon 06_Общие данные.doc
icon 06_Условные графические обозначения.dwg
icon 07_Структурная схема.dwg
icon 08_Схема соединений.dwg
icon 09_План расположения оборудования.dwg
icon 11_Задание на электроснабжение.doc
icon 11_Принципиальные однолинейные схемы.dwg
icon 12_Спецификация СКУД.doc

Additional information

Contents

Contents

1 General part

2 Purpose of the system

3 Basic Technical Solutions

4 Power supply and grounding of equipment

List of symbols, abbreviations and terms

Summary

The present document represents the explanatory note to the working draft of the Control and management system for access 17404049.4560243.077CC1.RD. The document includes information about the designed system, a description of the activity process, an overview of the main technical solutions and measures for preparing the automation object for system commissioning.

Confidential document of CJSC "CRIC incorporated." Any information provided in this document related to the cooperation of the parties, business activities or technical capabilities of CJSC "CRIC Incorporated," as well as to products, services, actual and analytical data, conclusions and materials, except for information that in accordance with the current legislation and other legal acts of the Russian Federation cannot be attributed to confidential information, is confidential. It is not permitted to copy and distribute information without the written permission of CJSC CRIC Incorporated.

General part

1.1 System name

Full system name: Access control and control system.

System symbol: MCDS.

1.2 Basis for Development

1.2.1 MCDS working design development works are performed in accordance with Contract No. D0714907 dated January 11, 2008.

1.3 Names of the Contractor and the Customer of the Works and their details

1.3.1 Contractor:

CJSC KROK Incorporated

Location: 105082, Moscow, Bolshaya Pochtovaya St., 26V house, building 2.

Postal address: 111033, Moscow,

st. Volochaevskaya, d. 15 K. 1.

Tel. (495) 9742274, fax (495) 917-22-77

1.3.2 Customer:

Rostpromstroybank (open joint stock company)

Address: 344029, Rostov-on-Don, Metallurgical St., d.102/2

1.4 List of regulatory and technical documents used in development

This working draft is developed in accordance with regulatory and regulatory technical documents:

VSN 6089 Communication, alarm and dispatching devices for engineering equipment of residential and public buildings;

GOST 21.10197 Basic requirements to design and working documentation;

GOST R 5039792 Electromagnetic hardware compatibility. Terms and definitions;

PUE 6.7 ed. Electrical Installation Rules;

RD 78.36.00299 Technical means of facilities safety systems. Symbols and schematic graphic elements of systems;

RD 78.36.0032002 Engineering and technical strengthening. Security equipment. Requirements and design standards for the protection of facilities from criminal encroachments;

RD 78.14693 Instruction on technical supervision of performance of design and installation works on equipment of facilities by means of security alarm;

SNiP 3.01.0185 * Organization of construction production ;

SNiP 3.05.0685 Electrical devices;

SNiP 12032001 Occupational safety in construction. Part 1. General requirements;

SNiP 12042002 Occupational safety in construction Part 2. Construction production;

Joint venture 1110195 Order of development, coordination, statements and structure of justifications of investments into construction of the enterprises, buildings and constructions;

Purpose of the system

2.1 The Access Control and Control System (ACMS) is a set of technical means designed to ensure authorized passage to the designated premises of the building, restricting access of various categories of employees and visitors to individual areas and/or premises of the building.

Key Technical Solutions

3.1 General System Solutions

3.1.1 Parsec (Russia) equipment with Russian Certificates of Conformity shall be used to build the access control and control system.

3.1.2 The following rooms shall be protected by the access control and monitoring system:

DPC room;

technical room.

3.1.3 MCDS allows to maintain up to 240 points of passage. Each system controller is focused on protecting one area of an object (room, floor, building).

3.1.4 The Parsec system is a combination of hardware and software.

3.1.5 NC1000 controllers are the main hardware part of ParsecNet network systems. These controllers provide one pass point.

3.1.6 The following equipment is connected to each controller:

readers;

exit buttons;

security sensors (hercones);

electromagnetic locks;

relays that allow to unlock all doors when a "fire" signal is received from the fire alarm system.

3.1.7 All controllers shall be combined into a single network having a star topology using the CNC8 central network controller.

3.1.8 "PNWin08" and "PNWinPI" software is installed on MCDS server (HP dc7800CMT computer located in the security room) to control the system and collect information during the system operation.

3.3 PNWin Software

3.3.1 . PNWin software runs Windows 95,

Windows 98, Windows NT version 4.x, Windows 2000 or Windows XP and supports in addition to the main, additional features:

a database of staff photographs;

graphical plans of alarm zones;

video verification;

Time and attendance accounting.

3.3.3 Active graphics plans provide direct control with the PC, both access functions and the security subsystem;

3.3.4 Central network controller (CNC8), allows connection of up to 240 controllers to one COM port of the PC;

3.3.5 Direct control of turnstiles is possible. Directly from the PC you can open the turnstile, both at the entrance and at the exit;

3.3.6 It is possible to extend the functionality of the system by connecting additional modules.

3.4 NC-1000 Access Controller

3.4.1 The NC1000 access controller (Figure 2) of the ParsecNET system is the main hardware part of the Parsec network system, supports the equipment of one pass point, as well as the room security alarm system associated with this pass point.

3.4.3 The controllers are supplied in a metal housing with a built-in power supply, which provides both power to the controller electronics and power to the locks.

General Instructions

1.1 The basis for the development of this project is Contract No. D0714907 dated January 11, 2008.

1.2 The project is developed taking into account the requirements of the SPDS.

1.3 Equipment provided in this project does not serve as sources of noise and vibration, which are dangerous to human health and life, and does not pollute the environment.

1.4 During operation of power supply equipment it is necessary to strictly observe the safety rules specified in the "Rules for operation of electrical installations of consumers" and "Rules for installation of electrical installations."

Power supply and grounding of equipment

2.1 Access control and monitoring system for reliability of power supply belongs to electric receivers of the first category.

2.2 MCDS power supply shall be performed from AC mains with frequency of 50 Hz with nominal voltage of 220 V, with TNCS grounding system in accordance with the assignment for power supply and grounding of MCDS equipment.

Installation Instructions

3.1 When installing the designed MCDS, use the Operating Manual and technical certificates for equipment.

Installation of wiring is carried out in accordance with this design taking into account the requirements of PUE, SNiP 3.05.0685.

Cable routes of the access control and monitoring system are performed:

RS485 data buses - FTP 4x2x0.53 twisted pair cable;

access point control lines - unshielded 4x0.5 KSPV cable;

power supply line of 12V lock - by 2x0.75 PVC cable;

the line of an emergency unblocking of doors at the fire - the J-Y (St) U1h2h0.8 cable.

Embedded devices for laying of cable routes shall be made as follows:

horizontal wiring of low-current cable routes shall be performed behind suspended ceilings in PVC pipe with corrugated diameter of 20 mm;

release to readers and buttons in the 10x22 box along the wall inside the protected rooms;

cables shall be lowered between floors in cable low-current risers in PVC pipe;

During installation of wiring it is not allowed:

Use non-insulated electrical wires

use cables and wires with damaged insulation;

combine low-current and high-current wiring in one pipe protection;

twist, tie the wires; glue sections of wires and cables with paper (wallpaper); use plinths, window and door wooden frames.

Location of equipment and cable routes may be changed by agreement with the Customer.

Construction and installation of cables and installation of equipment shall be carried out in compliance with safety and health measures.

The working project was developed in accordance with the current construction, technological and sanitary standards and regulations, provides for measures to ensure the constructive reliability, explosion and fire safety of the facility, protection of the population and sustainable operation of the facility in emergency situations, protection of the environment during its operation and meets the requirements of the law "On the basics of urban planning in the Russian Federation."

Drawings content

icon 06_Условные графические обозначения.dwg

06_Условные графические обозначения.dwg

icon 07_Структурная схема.dwg

07_Структурная схема.dwg

icon 08_Схема соединений.dwg

08_Схема соединений.dwg

icon 09_План расположения оборудования.dwg

09_План расположения оборудования.dwg

icon 11_Принципиальные однолинейные схемы.dwg

11_Принципиальные однолинейные схемы.dwg

Free downloading for today

Update after: 15 hours 24 minutes
up Up