Operation of Bulldozer B-10 on the trawl platform

  • Added: 04.04.2023
  • Size: 894 KB
  • Downloads: 0
Find out how to download this material

Description

Exercise

 

1. It is required to calculate the number of maintenance (TO) and repairs (P) of a construction machine to draw up an annual maintenance plan.

 

2. Develop an annual construction machine maintenance plan.

 

Initial data (Bulldozer B-10):

 

- the planned operating time is - 1400 moto-hours.

 

- the loader worked at the beginning of the planned year after a major overhaul - 3200 moto-hours;

 

- the frequency of overhaul of the loader is - 4800 hours;

 

- current repair - 960 hours;

 

- TO-2 - 240 hours;

 

- TO -1 - 50h.