Greenhouse (Winter Garden) - AC stage
- Added: 28.07.2022
- Size: 679 KB
- Downloads: 4
Description
GENERAL PART
The project is developed in accordance with the Design Task.
The working project is designed for construction in the 1V climatic region with the calculation of the winter temperature of the outside air -35 * C
Snow cover weight 1.00 kPa.
Wind head speed 0.38 kPa
Responsibility Class I,
degree of fire resistance II
ARCHITECTURAL AND PLANNING SOLUTION
The winter garden in the plan has an octagonal shape.
Overall dimensions 11,58х1,58m.
In the central part of the Winter Garden there is a recreation area marked with a podium.
The total height of the building h-5,850m
DESIGN SOLUTION
Foundations - Monolithic slab h=300 mm
Plinth - brickwork thickness b-250mm,
Exterior walls - wooden frame with slatted panel cladding
Basement KORPo-1NF/100/2,0/50 GOST 530-2007 with insulation with thermal insulation boards on a basalt basis according to GOST 9573-96, r-50kg/m3, b-100mm.
External walls - Wooden racks 50x150mm with insulation with heat-insulating boards on a basalt basis according to GOST 9573-96, r-50kg/m3, b-150mm.
Masonry should be carried out on cement-sand mortar M50 at an outside temperature not lower than
-3 C, at temperatures from -3 to -20 C on cement-sand mortar M100 with the addition of
plasticizers and antifreeze additives. External and internal walls reinforced with mesh
∅5VR I with 50x50mm cells through 5 rows of masonry. Mesh weight 9,7kg/m3.
From the inside, the exterior walls are plastered with a cement-sand mortar M50 with a thickness of 15 mm (high-
quality plaster. Fasten the insulation with fishunkers 5pcs. per 1m2.
The roof is asphalt shingles.
Gutter - external organized.
Stained glass windows - aluminum with thermal protection.
Interior decoration of the premises - porcelain stoneware, granite, wooden slatted panels.
Exterior finish - brush with marble chips
Floors - porcelain stoneware
Blind - concrete on crushed stone base h-50mm and sand h-100mm, width 500mm
FIRE PREVENTION MEASURES
Fire-fighting measures were carried out in full compliance with the SNiP RK 2.02.01-2001 "Fire safety of buildings and structures"