Course work on TSP "Zero Cycle Works"
- Added: 17.05.2015
- Size: 737 KB
- Downloads: 1
Description
Project's Content
|
08-535.dwg
|
08-535.doc
|
Additional information
Contents
Contents
Course Job Error! Bookmark is not defined
General provisions
1. Initial data for development of course work: soil characteristics
2. Calculation of excavation volumes
2.1. Determination of earth structure type and parameters
2.2. Calculation of excavation volumes
3. Calculation of a set of construction machines
3.1. Calculation of parameters of penetrations of the leading excavating machine
3.2. Selection of type and quantity of vehicles for soil removal
3.3. Selection of mechanization tools for backfilling and soil compaction
4. Technical and economic calculations
4.1. Calculation of labor costs and machine time (calculation of labor costs, schedule)
Labor and Machine Time Cost Sheet
Work Schedule
4.2. Determination of productivity and cost of one machine-hour of operation of the leading excavating machine
5. Safety precautions
6. Recommended Literature
Project Description
The project considers construction and installation work on the construction of the foundations of an industrial building :
cutting off the vegetable layer;
excavation of soil in trenches and pits for installation of prefabricated foundations;
rework and cleaning of pit bottom, installation of foundations for sand preparation;
transportation of soil to the dump by dump trucks;
bulldozing of foundation sinuses with soil compaction by hand by 50 cm from foundation body and ramming of the rest of soil by mechanical ramming machines.
The project under development does not consider the construction of a control geodetic network, water reduction, temporary roads, storage sites, temporary engineering networks, household and utility rooms.