• RU
  • icon Waiting For Moderation: 0
Menu

Course project - OSB of a 9-storey 72-apartment residential building with an area of 634.8 m2

  • Added: 17.05.2024
  • Size: 946 KB
  • Downloads: 0
Find out how to download this material

Description

Contents
Introduction
1 Scheduling
2 List of labor costs and machine time
3 Methods of organizing construction production
4 Network Diagram Identifier Card
5 Network Diagram Calculation
5.1 Calculation of time parameters of the network schedule
5.2 Building a graph of resource requirements
6 Schedule Workers' Needs
7 Standard construction period
8 Development of the construction master plan
8.1. General requirements for the design of the construction master plan
8.2 Crane selection, binding and definition of operating areas
8.3 Design of temporary roads, placement of temporary buildings and communications on the construction site
8.4 Calculation of the area of temporary buildings and structures
8.5 Calculation of the area of temporary warehouses for the storage of materials, products and structures
8.6 Water supply of the construction site
8.7 Calculation of temporary power supply
9 Technical and economic indicators
Conclusion
References

Source data

Pitch.

Name

Object

Built-up area, m2.

Builds.

volume

cubic meters

The construction of the month.Preparation period, months

Under-

zemn.

part

Per month.

Above-

zemn.

part

Per month.

Finishing, months
3

9-storey 72

apartment residential building.

634,816150101252

Conclusion
A project for organizing the construction of a 9-storey 72-apartment residential building has been completed.
A description of the architectural and structural solutions of the structure was carried out, a calendar plan for the construction of the facility    was developed.
A list of labor costs and machine time    , a card-determiner of the network schedule is given. The choice of methods for organizing construction production, the calculation of the network schedule, the description of the type and structure of the schedule are made  . Calculations were made according to the schedule of workers' needs.
The standard construction period has also been determined. A construction master plan has been designed.
Main technical and economic indicators of the project:
- labor intensity of construction and installation works – 26095 man-days;
- labor intensity of construction and installation work per unit of final product – 1.62 man-days/m3, 4.8 man-days/m2;
- indicator of the use of the area of the master plan for temporary buildings, structures and devices. – 0,32;
- average number of workers Ncp – 13 people;
- estimated (planned in the project) duration of construction according to the calendar schedule – 9.6 months.
Thus, it can be concluded that the solution of the tasks set in the course project is complete. 
The practical orientation of the work and the scope of its application lies in the possibility of carrying out the project in nature.

Project's Content

icon
icon ОСП.docx
icon ОСП.dwg

Free downloading for today

Update after: 1 hour 30 minutes
up Up